Delivery of the Main Electrical Equipment to the Construction Site Is Continuing
The company continues to make steady progress on the "Power Supply for the Metallurgical Complex under Construction" project, which is being implemented on a turnkey basis. Following the delivery of the power transformers, the next set of key electrical equipment has now arrived at the construction site.
The delivery includes 6 kV, 4,000 A current-limiting reactors for the medium-voltage part of the power supply system. The 110 kV outdoor switchgear has also been delivered. Construction work on site is proceeding as planned. The newly delivered equipment will be installed and commissioned at the next stages of the project. Together with the power transformers, it forms the backbone of the power supply system that will provide reliable and uninterrupted electricity to the facilities of the new metallurgical complex.